Preparatory Groundworks Underway

3 October 2024

As the application for new development at the Park continues to make good progress through planning, consent has been given to undertake preparatory groundworks on the site at the northern end of the Park.
 
Contractors J Mould have been appointed with the task of identifying, removing and backfilling existing underground slabs and previous foundations. Underlying services unearthed in this process will be capped and removed, together with any external drainage and manholes. The area will be backfilled with crushed materials reused from the site to reduce vehicle movements and finally levelled off to complete the works.
 
Work is scheduled to start on 7 October and will take around 12 weeks.
 
 